
The context
- 
Electrical accessories company witnessing 50% drop in Sales, high quality complaints with market returns at 14% of Sales
 - 
Production planning focused on capacity utilization and batch processing, with more than half of customer orders not being fulfilled
 - 
Low employee morale, high inventory of 8 months and cash losses
 

THE SOLUTION
- 
Lean Manufacturing initiative with multiple process streamlining and team performance optimization waves deployed
 - 
Manufacturing and Sales teams trained on Waste identification and elimination
 - 
SKU changeover times shortened, and assembly cycle times reduced through single piece flow
 

THE IMPACT
- 
SKU changeover times shortened, and assembly cycle times reduced through single piece flow thereby improving productivity and reducing standard costs
 - 
Market returns reduced to 3% with delivery performance at 92%, and finished goods inventory of only 3 weeks
 - 
Attrition rates radically brought down from 70% to 20%
 
